| Client: |
Aspen Planers Sawmill
Merritt BC |
 |
| Project: |
Fire Rebuild for Edger-Optimizer System.
|
| Details: |
A fire in the mill destroyed the edger/optimizer wiring and several power and control devices including, servo valves, Temposonic probes and other equipment. Pacificon was engaged to provide Aspen Planers with a replacement control system for the fire damaged equipment. An upgrade to Controllogix from the existing PLC5 system was also completed.
|
| Notes: |
Pacificon successfully delivered all the hardware and software necessary to restart the edger optimizer line in less than 3 weeks |
|