The Company

Services

Projects

Products

Clients

Careers

Contact Us

Search

 

Pacificon Systems Ltd.

 

Tel:

1-604-525-5295

Fax:

1-604-525-5955

 

psl@pacificon.com

Sawmill Industry

 

SIMPSON TIMBER COMPANY .......................................................................1996 - 2006

Korbel, California

Planer Mill Re-build

 

From concept to commissioning, this 14-month project started with the removal of all the existing planermill mechanical equipment except the Planer, Tray Sorter, Wet Stacker and one Strapper that were re-used.  In addition, all the MCC’s and PLC’s were removed and replaced with 2100 CenterLine MCC’s and ControlLogix PLC’s from Allen Bradley.  SKS supplied the engineering services and USNR and COE/Newnes supplied most of the mechanical equipment.  Pacificon was responsible for the entire control system design and commissioning.

 

The following mechanical equipment was installed:  

  • Continuous Tilt Hoist (USNR)

  • Wet Stacker (re-used)

  • Planer (reused)

  • Residual Conveyor System for sawdust and chips

  • Bag House system

  • Re-entry hoist

  • Linear High Grader (planer outfeed optimizer) *

  • 3 Operator grading stations *

  • 3-stage servo-controlled fence *

  • 6 to 20 foot Trimmer *

  • 20-tray sorter (reused)

  • Servo-controlled electronically-geared sorter drive system c/w skip-a-lug & cut-in-two feature

  • Automated 2-layer sorter removal chains c/w Spray Booth

  • High-speed servo motor and hydraulic linear positioner controlled lumber stacker *

  • Two lumber strappers (including one re-used)

  • Two paper wrap stations

* Note:  Only the mechanical equipment and optimizing system was supplied by COE/Newnes

 

Pacificon’s Project Tasks 

  • Design and program automated controls for all above equipment

  • Fabricate and supply all control panels and operator stations

  • Commission all vendors equipment

Control Equipment Summary provided by Pacificon 

  • 3 ControlLogix PLC’s were used to control the Planer Infeed Area, Trim-Sort Line and Package Handling areas

  • 2 additional ControlLogix PLC’s were used for specialized motion control for the following equipment throughout the plant:

    • 10 electric servo drives

    • 12 hydraulic linear positioners

  • 9 Ethernet PLC modules were used to provide multiple Ethernet networks for interfacing to all the I/O points, HMI's and MCC's

  • four 8-port and seven-24-port managed switches were used at 3 locations with redundant fiber-optic cables between the 3 locations

  • 2950 I/O points required nine 17-slot racks & 18 different Flex I/O drops for consoles, panels, etc.

  • all I/O devices were connected via Ethernet rather than conventional Remote or ControlNet I/O

  • 34 VFD's were controlled by an embedded Ethernet interface module in each VFD

  • 150 standard drives, each controlled by a DeviceNet E3 or E3 Plus module

  • 10 MCC's interfaced to PLC via 10 EtherNet to DeviceNet (EN2DN) converters

  • 7 Panelview 400 Plus HMI’s with Ethernet interface for local status and alarm messages

  • RSView HMI station for trimmer & sorter setup & diagnostics via Ethernet interface

  • client supplied Sorter Setup and Reporting system via Ethernet interface

  • connected to corporate network for remote access and troubleshooting via web

Even though this project was only designed for 130 lugs per minute (LPM) (2" x 4" lumber to 4" x 12" timbers were processed on the same line), we are also experienced with 200 LPM equipment and the special design considerations that are required for a control system to run at these higher speeds.

 

 

End Dogger for Fir and Redwood Products

Pacificon assumed full system responsibility to:

  • Replace existing H.P. computer based controls with Allen-Bradley PLC 5/40E based system

  • Completely rewired machine - Block I/O modules used extensively to reduce wiring costs

  • Replaced X-Y scanner (high maintenance photocell array) with two Perceptron Lasar scanners

  • Replaced USNR optimizing system with Perceptron optimizing system

  • Visual Basic 6.0 operator interface for system set-up and display of cutting solution and diagnostics

  • Productivity increased by more than 10 % (back end of mill cannot keep up for true test)

  • Recovery increased by 3%

  • Upgraded hydraulic system and charger positioners in July 2001

Barker and Log Merchandizing Systems for Fir and Redwood Products 

  • Replace existing H.P. computer based log bucking and sorting functions with PLC-based system

  • Upgrade Texas Instruments PLC system to Allen-Bradley PLC 5/40

  • Replace two 4-foot Opcon diameter scanners with scanners from Banner

  • Visual Basic 6.0 operator interface used for system set-up and diagnostics and to display bucking solution

Log Quad

  • Replaced Texas Instruments PLC and ATI setworks controller with Allen-Bradley PLC 5/20 and 3 QB modules to control hydraulic linear positioners on four (4) saws, picker and newly added slabber in front of saws to remove flare on butt of logs.

  • Panelmate 1500 colour LCD added for operator interface, diagnostics and size changes.

Tandem Horizontal Resaw

  • Replaced Texas Instruments PLC and Inovec setworks controller with Allen-Bradley PLC 5/20 and QB module to control two (2) saw positioners.

  • Panelmate 1500 colour LCD added for operator interface, diagnostics and size changes.

 

 

CANADIAN FOREST PRODUCTS LTD. .......................................................2001 - 2002 

Rustad Division

Prince George, BC

  

Konus Twin Burner Thermal Oil Plant Upgrade

  • Upgraded existing Frank Controls microprocessor based system with a PLC 5 controller

  • All PID Loop controls were performed in the PLC rather than with add-on controllers

  • Several motors starters were upgraded to VFD's with speed control from the PLC program

  • Touch screen computer for Operator Interface with Ethernet interface to PLC

  • User friendly, RSView 32 operator interface used for manual and automatic controls, alarms and historical trending

  • System included diesel backup oil pump and supplementary pellet fuel system

  • Most of the existing process measurement devices were retained with several new 4-20ma transmitters installed

  • Upgrades for each burner were successfully completed over two 4-day shutdowns

Sorter PLC Upgrade 

  • Upgraded existing Trimmer, COE Optimizer and NAC 62-Bin Sorter controls with Allen-Bradley PLC 5/60 and RS View 32 system.

  • Completely rewired sorter and replaced all bin control panels and field devices.

  • State of the art configuration and diagnostic screens are used extensively throughout the system.

  • Very user friendly system taking full advantage of latest hardware and software technologies to provide many reporting and diagnostic capabilities not possible in real time with previous products.

  • Advanced features have been made possible through the use of standard high speed PC computers and ethernet network, as well as the extended memory available in PLC’s today.

  • Project Management by International Quest Engineering and installation by K2 Electrical Contractors.

 A complete colour demo package is available for presentation purposes.

 

HEATWAVE TECHNOLOGIES Inc.................................................................2001 – 2002

Vancouver and Crescent Valley, BC

 

Two projects were completed:

RF Oven Controls (prototype for food industry)

  • Two Parker Linear positioners controlled with Allen Bradley Ultra 3000 Indexing drives used for adjusting the RF tuning

  • PID loops controlled by PLC

  • FlexLogix processor with DeviceNet interface to drives and RF power source

  • Computer running Intellution / iFix for operator interface

RF Kiln Controls (lumber drying system for Hampton Forest Products - Randle, Wash.)

  • Four Stepper motor positioners were controlled with API Motion Controls drives and were used for adjusting capacitors used in the two RF tuning loops

  • Two RF sections were used to provide the thermal energy requirements for the large lumber drying kiln

  • ControlLogix processor controlling several PID loops with over 40 analog I/O points and over 240 digital I/O points

  • Extensive DeviceNet interface (24 nodes) to control remote racks and 13 motor using Cutler Hammer starters

  • RSView ME used for operator interface (supplied by customer)

 

FLAVELLE SAWMILL COMPANY.............................................................................2002

Port Moody, BC

 

Sorter PLC Upgrade

  • Upgrade an existing NAC 35-bin sorter controls with Modicon Quantum PLC and Visual Basic/Windows2000 set up & reporting system with two large production / message displays

  • This is a second Sorter in the sawmill that sat dormant for the past 8 years.  We had to replace the thickness and width/position encoders but were able to re-use most of the existing wiring and other sensors

  • This Quantum sorter package has the ability to operate two sorters from the same PLC processor and uses one Operator Interface (HMI)

  • Unlike most other HMI's, the HMI is not required to be on-line while the sorter is running as all shift report data is stored in the PLC memory.  Therefore, the HMI computer can also serve as a PLC programming terminal

  • These features were attractive to the customer and as a result, there is a good chance Pacificon will convert the other sorter thereby eliminating the second computer and PLC processor

 

L&M LUMBER LTD. ..........................................................................................2001 – 2002

Vanderhoof, BC

Moisture Sort System – Process Control Upgrade

  • High Speed (200 LPM) moisture sort line complete with stacker for studmill

  • Allen-Bradley PLC 5/20E

  • RS View 32 HMI for diagnostics and easy access to all system parameters

  • Dual Message Display Boards

  • Northern Mill Industries (NMI) Moisture Sort System

  • Project management and mechanical design by Stolberg Engineering Ltd.

 

 

ASPEN PLANERS  ......................................................................................................2001

Merritt, BC

Gang Edger 

  • Electrical rebuild after fire destroyed machine wiring and several power and control devices including D.C. motors, servo valves, Temposonic probes, etc.

  • D.C. drives replaced and upgraded

  • Saw position lasers and saw positioners were completely re-built and rewired

  • Program modifications to an Allen-Bradley PLC 5 program. Up-dated drawings and documentation.

 

 

CRESTBROOK FOREST PRODUCTS.................................................................... 2000

Cranbrook, BC

  • Provided commissioning assistance for client’s finger jointing plant designed by Lucidyne

  • System included thirty (30) networked computers communicating to a Multi-Processor (3)Allen-Bradley Control Logix PLC control system

 

 

WEYERHAEUSER (was M&B)............................................................................. 1999 - 2001

Canadian White Pine Division

Vancouver, BC

 

Two 44-bin Sorters in sawmill for cedar products

  • Laser based differential thickness sensors – a Pacificon Systems design

  • Two (2) Grade Mark Readers – supplied by Cypress Technology

  • Two (2) Stackers with auto fill stick hoppers

  • Modicon Quantum PLC with Panelmate operator interface for motor control and diagnostics

  • Six alphanumeric scrolling message displays used throughout sawmill

  • Visual Basic 6.0 / Windows based operator interface setup and reporting system

  • Ticket Printer – to print status of each package (Bin No., Grade, Length, FBM, etc.)

Bull Saw and Timber Handling System

  • Timber scanning and tally system added with scrolling alphanumeric production display

  • Timber grade tracking and inkjet printing system

 

 

MILLAR WESTERN..................................................................................................... 2000

Whitecourt, Alberta

 

New Dual-Ring Nicholson Debarker

  • Replaced existing Modicon PLC system with Allen-Bradley Control Logix PLC System

  • Controlnet interface to several new VFD’s

 

 

INTERFOR............................................................................................................ 1998 - 2000

Squamish, BC

 

Twin Vertical Resaw and Twin Horizontal Resaw, both with:

  • Allen-Bradley PLC 5/30 with two QB modules

  • Panelmate Interface for motor control, diagnostics and setworks configuration

 

 

ASPEN PLANERS............................................................................................... 1995 -1996

Merritt, BC

 

Edger Optimizer & Resaw

  • Supplied complete Allen-Bradley PLC 5/40 system, Panelmate, consoles etc. for one operator to control both Edger Optimizer and Resaw machine centres.

  • Ten (10) linear positioners controlled by QB modules.

  • Responsible for PLC Interface to Scanner and Optimizer supplied by Newnes.

 

 

The next four projects are similar in nature:  i.e. Pacificon’s PLC programming expertise was requested by the following clients to expedite another vendor’s program installation and start-up.  Lengthy delays by the original vendor had caused production shortfalls and the client’s were anxious to get the mill operating efficiently.

 

 

TIMBERWEST............................................................................................................... 2001

Campbell River, BC – Dimension Products Mill

Double Length Infeed (DLI) Line

  • On site PLC consulting and start-up assistance (original program provided by another vendor)

  • Mill was also experiencing the same production rate issues as following projects

 

 

INTERFOR - FLAVELLE CEDAR DIV. (now owned by Mill & Timbers)............. 1997 - 1998

Port Moody, BC – Cedar and Fir Dimension Products Mill

 

Barker, Log Bucking and Double Length Infeed (DLI) Line

  • On site PLC consulting and start-up assistance (original program provided by another vendor).

  • Nine (9) months after the sawmill modernization, mill personnel were still struggling to achieve the desired target goals.  Production rates were 13.5% below targets.

  • Considerable program modifications to the entire system to increase production levels.

  • PLC documentation added to assist mill electricians with “in-house” troubleshooting.

  • A performance bonus was received after increasing production rate by 18% in three (3) months to meet sawmill monthly target goal.  During the last 2 months, the production rate was increased by a further 10%, surpassing all expectations.  In fact, there have been a few days when production was close 250,000 FBM/shift, with the target being 190,000 FBM/shift.

 

 

AVENOR INC....................................................................................................... 1997 - 1998

Ear Falls, Ontario - Stud Mill

 

Small and Large Double Length Infeed (DLI) Lines

  • On site PLC consulting and start-up assistance (original program provided by another vendor).

  • Mill was experiencing the same low production rates as Flavelle Cedar (see above).

 

 

RIVERSIDE FOREST PRODUCTS................................................................. 1997 - 1998

Williams Lake, BC - Stud Mill

 

Double Length Infeed (DLI) Line

  • On site PLC consulting and start-up assistance (original program provided by another vendor).

  • Mill was also experiencing the same low production rates as mentioned above.


back to top